PRINCE2Practitioner 試験問題 91
A new Training Delivery Manager is being recruited to replace the current manager in six month's time. The new Training Delivery Manager will need to review the 'classroom-based training materials' before they are finalized. As a result, the Chief Executive Officer (CEO), who is not part of the project management team, has stated that the project's duration should be at least seven months. Any deviations from this timescale must be escalated to the CEO.
Is this an appropriate application of the 'manage by exception' principle, and why?
Is this an appropriate application of the 'manage by exception' principle, and why?
PRINCE2Practitioner 試験問題 92
プロジェクトシナリオ - 健康と安全のトレーニングプロジェクト:
ABC 社は、標準モデルを使用してトレーニング教材を開発し、顧客にコースを提供する、定評のあるトレーニング会社です。
ABC社は、建設現場における健康と安全に関する政府の法規制の最近の改正に対応するためのプロジェクトを委託しました。このプロジェクトは、教室での研修とeラーニングに必要な教材を含む「健康と安全に関する研修を提供する能力」を提供します。建設会社にとって期待されるメリットは、休業日数と事故による訴訟費用の削減です。
eラーニングコースは、外部の専門コンサルタント会社によって開発されます。教室型トレーニング用の教材は、ABC社の開発チームが提供します。すべてのコース教材は、使用前にパイロットテストを実施します。ABC社は、顧客へのトレーニングを提供するだけでなく、他のトレーニング会社へのコース教材の販売も検討しています。ABC社は、自社の営業・マーケティング部門を活用してコースのプロモーションを行います。
この法律は、建設会社に対し、2年以内に新法に準拠することを義務付けています。コースを実施するには、コース教材と講師が政府機関の認定を受ける必要があります。
ABC 社は、プロジェクト開始から 5 か月以内にパイロット コースを提供する予定です。
ABC 社の新しいコースの標準開発モデルでは、次の段階が推奨されています。

プロジェクトシナリオの終了。
追加情報:
最高経営責任者(CEO)は5年前に会社を設立しました。彼女のリーダーシップの下、ABC社は急速に成長し、成功を収めた研修会社となりました。同社は、認定を受けた幅広い専門研修を提供しています。
財務部長はABC社の創設メンバーでもあり、運用チームと開発チームの予算承認を担当しています。彼女はすべての大規模契約を自ら承認します。
購買マネージャーは財務ディレクターに報告し、サプライヤー契約の管理と監視を担当します。
オペレーションディレクターは、すべてのトレーニングの実施とトレーニング開発予算の管理に責任を負います。彼の部署は、コース、会場、トレーナーを手配します。彼らは製品チームおよび営業チームと連携し、包括的なトレーニングスケジュールを提供します。ABC社のITマネージャーは、オペレーションディレクターに報告します。
ビジネス開発ディレクターは、新たな研修ニーズの特定と新製品の提案を担当するため、最近任命されました。彼女はオペレーションディレクターと連携し、コスト意識の高いアプローチと、安全衛生コースに適切な開発技術が使用されるよう努めます。
トレーニング開発マネージャーはビジネス開発ディレクターに報告し、標準コース開発モデルに従ってトレーニング教材の開発と認定取得を担当します。彼のチームのコース開発者は、幅広い開発技術のスキルを有しており、必要に応じてプロジェクトに割り当てられます。
トレーニング・デリバリー・マネージャーは、オペレーション・ディレクターに報告し、社内および社外のトレーナーがABC社のトレーニングコースを必要な基準に沿って実施することを保証する責任を負います。また、コース教材が目的に適合し、必要な品質を満たしていることを確認するためにも、トレーニング・デリバリー・マネージャーは責任を負います。
セントラルサービスディレクターは、コーポレートコミュニケーション、施設管理、構成管理を担当しています。彼は最近、社内の全品質システムを単一の品質管理システムに統合し、コーポレート品質部門を設立するプロジェクトを主導しました。この部門は現在、コーポレート品質マネージャーによって管理されています。
コーポレートドキュメントマネージャーは、セントラルサービスディレクターに直属しています。彼女は社内のドキュメント管理システムの構築に貢献し、現在はそれを全社的に運用しています。また、管理者チームを管理し、作業負荷が高いときにはスタッフと契約社員を派遣しています。
営業部長は2ヶ月前にABC社に入社し、コースや教材を活かせる新たな市場開拓を提案することで、自身の地位を確立することに熱心です。すべてのアカウントマネージャーとマーケティングチームは彼に報告しており、既存のトレーニングコースを他のトレーニング会社や既存顧客に宣伝しています。
追加情報の終わり。
パイロットコースの提供は、「計画パイロットコース」と「
「実施済みパイロットコース」。「計画済みパイロットコース」はステージ3で作成され、「実施済みパイロットコース」はステージ4で実施されます。これにより、パイロットコースの実施に必要なリソースが確保される前に、プロジェクト委員会がパイロットコースの計画を承認できるようになります。
プロジェクトを制御するための計画テーマの適用がなぜこれが適切であるのでしょうか?
ABC 社は、標準モデルを使用してトレーニング教材を開発し、顧客にコースを提供する、定評のあるトレーニング会社です。
ABC社は、建設現場における健康と安全に関する政府の法規制の最近の改正に対応するためのプロジェクトを委託しました。このプロジェクトは、教室での研修とeラーニングに必要な教材を含む「健康と安全に関する研修を提供する能力」を提供します。建設会社にとって期待されるメリットは、休業日数と事故による訴訟費用の削減です。
eラーニングコースは、外部の専門コンサルタント会社によって開発されます。教室型トレーニング用の教材は、ABC社の開発チームが提供します。すべてのコース教材は、使用前にパイロットテストを実施します。ABC社は、顧客へのトレーニングを提供するだけでなく、他のトレーニング会社へのコース教材の販売も検討しています。ABC社は、自社の営業・マーケティング部門を活用してコースのプロモーションを行います。
この法律は、建設会社に対し、2年以内に新法に準拠することを義務付けています。コースを実施するには、コース教材と講師が政府機関の認定を受ける必要があります。
ABC 社は、プロジェクト開始から 5 か月以内にパイロット コースを提供する予定です。
ABC 社の新しいコースの標準開発モデルでは、次の段階が推奨されています。

プロジェクトシナリオの終了。
追加情報:
最高経営責任者(CEO)は5年前に会社を設立しました。彼女のリーダーシップの下、ABC社は急速に成長し、成功を収めた研修会社となりました。同社は、認定を受けた幅広い専門研修を提供しています。
財務部長はABC社の創設メンバーでもあり、運用チームと開発チームの予算承認を担当しています。彼女はすべての大規模契約を自ら承認します。
購買マネージャーは財務ディレクターに報告し、サプライヤー契約の管理と監視を担当します。
オペレーションディレクターは、すべてのトレーニングの実施とトレーニング開発予算の管理に責任を負います。彼の部署は、コース、会場、トレーナーを手配します。彼らは製品チームおよび営業チームと連携し、包括的なトレーニングスケジュールを提供します。ABC社のITマネージャーは、オペレーションディレクターに報告します。
ビジネス開発ディレクターは、新たな研修ニーズの特定と新製品の提案を担当するため、最近任命されました。彼女はオペレーションディレクターと連携し、コスト意識の高いアプローチと、安全衛生コースに適切な開発技術が使用されるよう努めます。
トレーニング開発マネージャーはビジネス開発ディレクターに報告し、標準コース開発モデルに従ってトレーニング教材の開発と認定取得を担当します。彼のチームのコース開発者は、幅広い開発技術のスキルを有しており、必要に応じてプロジェクトに割り当てられます。
トレーニング・デリバリー・マネージャーは、オペレーション・ディレクターに報告し、社内および社外のトレーナーがABC社のトレーニングコースを必要な基準に沿って実施することを保証する責任を負います。また、コース教材が目的に適合し、必要な品質を満たしていることを確認するためにも、トレーニング・デリバリー・マネージャーは責任を負います。
セントラルサービスディレクターは、コーポレートコミュニケーション、施設管理、構成管理を担当しています。彼は最近、社内の全品質システムを単一の品質管理システムに統合し、コーポレート品質部門を設立するプロジェクトを主導しました。この部門は現在、コーポレート品質マネージャーによって管理されています。
コーポレートドキュメントマネージャーは、セントラルサービスディレクターに直属しています。彼女は社内のドキュメント管理システムの構築に貢献し、現在はそれを全社的に運用しています。また、管理者チームを管理し、作業負荷が高いときにはスタッフと契約社員を派遣しています。
営業部長は2ヶ月前にABC社に入社し、コースや教材を活かせる新たな市場開拓を提案することで、自身の地位を確立することに熱心です。すべてのアカウントマネージャーとマーケティングチームは彼に報告しており、既存のトレーニングコースを他のトレーニング会社や既存顧客に宣伝しています。
追加情報の終わり。
パイロットコースの提供は、「計画パイロットコース」と「
「実施済みパイロットコース」。「計画済みパイロットコース」はステージ3で作成され、「実施済みパイロットコース」はステージ4で実施されます。これにより、パイロットコースの実施に必要なリソースが確保される前に、プロジェクト委員会がパイロットコースの計画を承認できるようになります。
プロジェクトを制御するための計画テーマの適用がなぜこれが適切であるのでしょうか?
PRINCE2Practitioner 試験問題 93
このプロジェクトの責任者として CEO を任命する必要がある理由を説明する 2 つの文はどれですか。
PRINCE2Practitioner 試験問題 94
プロジェクトシナリオ - 健康と安全のトレーニングプロジェクト:
ABC 社は、標準モデルを使用してトレーニング教材を開発し、顧客にコースを提供する、定評のあるトレーニング会社です。
ABC社は、建設現場における健康と安全に関する政府の法規制の最近の改正に対応するためのプロジェクトを委託しました。このプロジェクトは、教室での研修とeラーニングに必要な教材を含む「健康と安全に関する研修を提供する能力」を提供します。建設会社にとって期待されるメリットは、休業日数と事故による訴訟費用の削減です。
eラーニングコースは、外部の専門コンサルタント会社によって開発されます。教室型トレーニング用の教材は、ABC社の開発チームが提供します。すべてのコース教材は、使用前にパイロットテストを実施します。ABC社は、顧客へのトレーニングを提供するだけでなく、他のトレーニング会社へのコース教材の販売も検討しています。ABC社は、自社の営業・マーケティング部門を活用してコースのプロモーションを行います。
この法律は、建設会社に対し、2年以内に新法に準拠することを義務付けています。コースを実施するには、コース教材と講師が政府機関の認定を受ける必要があります。
ABC 社は、プロジェクト開始から 5 か月以内にパイロット コースを提供する予定です。
ABC 社の新しいコースの標準開発モデルでは、次の段階が推奨されています。

プロジェクトシナリオの終了。
追加情報:
最高経営責任者(CEO)は5年前に会社を設立しました。彼女のリーダーシップの下、ABC社は急速に成長し、成功を収めた研修会社となりました。同社は、認定を受けた幅広い専門研修を提供しています。
財務部長はABC社の創設メンバーでもあり、運用チームと開発チームの予算承認を担当しています。彼女はすべての大規模契約を自ら承認します。
購買マネージャーは財務ディレクターに報告し、サプライヤー契約の管理と監視を担当します。
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company' s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
RISK
The project is in stage 2. The project manager has heard that a competitor may launch a similar e-learning course much sooner than ABC Company. There is a threat that the earlier launch of a competitor's course may reduce the profitability of ABC Company training courses.
Here are three responses to this risk.
Which risk response type (A-F) are they?
Choose only one response type for each risk response. Each response type can be used once, more than once, or not at all.

ABC 社は、標準モデルを使用してトレーニング教材を開発し、顧客にコースを提供する、定評のあるトレーニング会社です。
ABC社は、建設現場における健康と安全に関する政府の法規制の最近の改正に対応するためのプロジェクトを委託しました。このプロジェクトは、教室での研修とeラーニングに必要な教材を含む「健康と安全に関する研修を提供する能力」を提供します。建設会社にとって期待されるメリットは、休業日数と事故による訴訟費用の削減です。
eラーニングコースは、外部の専門コンサルタント会社によって開発されます。教室型トレーニング用の教材は、ABC社の開発チームが提供します。すべてのコース教材は、使用前にパイロットテストを実施します。ABC社は、顧客へのトレーニングを提供するだけでなく、他のトレーニング会社へのコース教材の販売も検討しています。ABC社は、自社の営業・マーケティング部門を活用してコースのプロモーションを行います。
この法律は、建設会社に対し、2年以内に新法に準拠することを義務付けています。コースを実施するには、コース教材と講師が政府機関の認定を受ける必要があります。
ABC 社は、プロジェクト開始から 5 か月以内にパイロット コースを提供する予定です。
ABC 社の新しいコースの標準開発モデルでは、次の段階が推奨されています。

プロジェクトシナリオの終了。
追加情報:
最高経営責任者(CEO)は5年前に会社を設立しました。彼女のリーダーシップの下、ABC社は急速に成長し、成功を収めた研修会社となりました。同社は、認定を受けた幅広い専門研修を提供しています。
財務部長はABC社の創設メンバーでもあり、運用チームと開発チームの予算承認を担当しています。彼女はすべての大規模契約を自ら承認します。
購買マネージャーは財務ディレクターに報告し、サプライヤー契約の管理と監視を担当します。
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company' s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
RISK
The project is in stage 2. The project manager has heard that a competitor may launch a similar e-learning course much sooner than ABC Company. There is a threat that the earlier launch of a competitor's course may reduce the profitability of ABC Company training courses.
Here are three responses to this risk.
Which risk response type (A-F) are they?
Choose only one response type for each risk response. Each response type can be used once, more than once, or not at all.

PRINCE2Practitioner 試験問題 95
費用対効果の高いソリューションが常に再評価されるようにする責任は誰にありますか?