CGEIT 試験問題 326
You work as a project manager for BlueWell Inc. Your project is using a new material to construct a large warehouse in your city. This new material is cheaper than traditional building materials, but it takes some time to learn how to use the material properly. You have communicated to the project stakeholders that you will be able to save costs by using the new material, but you will need a few extra weeks to complete training to use the materials. This risk response of learning how to use the new materials can also be known as what term?
CGEIT 試験問題 327
Which of the following would be MOST useful for prioritizing IT improvement initiatives to achieve desired business outcomes?
CGEIT 試験問題 328
企業の IT ガバナンスを成功させるには、IT ポリシーの主な焦点は次のどれにすべきでしょうか?
CGEIT 試験問題 329
Which of the following is the PRIMARY purpose of an effective set of key risk indicators (KRIs)?
CGEIT 試験問題 330
Which of the following is the BEST course of action to enable effective resource management?