C_TS452 試験問題を無料オンラインアクセス
| 試験コード: | C_TS452 |
| 試験名称: | SAP Certified - SAP S/4HANA Cloud Private Edition, Sourcing and Procurement |
| 認定資格: | SAP |
| 無料問題数: | 200 |
| 更新日: | 2026-07-18 |
<strong>CHALLENGE 1 — Supplier Allocation Readiness for Shared Material Demand</strong> During cutover rehearsal, two plants generate recurring demand for the same packaging material family. Both plants have approved suppliers available, but only one plant follows the expected supplier distribution pattern once purchase documents are created. The sourcing lead wants to preserve a shared support model after go-live rather than rely on local buyer judgment.
What is the best first validation action?
A consumer electronics company is validating subcontracting procurement in SAP S/4HANA Cloud Private Edition during a rollout from a template that previously handled the process outside the core system. Purchase requisitions and purchase orders for subcontracting materials can be created successfully, and component visibility appears correct in the buyer-facing apps. However, when the team posts goods receipt for finished items from one subcontractor group, the follow-on accounting validation fails only for those receipts. The same subcontracting flow works for another subcontractor group in the same company code.
The project lead wants the process fixed within standard configuration because the next rollout wave will reuse the same template. Manual finance corrections are not allowed, and clean core governance prevents any custom posting logic.
What should the consultant check first?
A consumer-packaging company is validating centrally governed source-list usage in SAP S/4HANA Cloud Private Edition for a business unit that is retiring a spreadsheet-based sourcing tracker. Buyers can create and release the relevant sourcing records, and approved purchase requisitions are available for conversion. For most material families, purchase-order creation correctly proposes the intended governed source. However, for one seasonal material family, the system proposes a valid supplier but ignores the source priority expected from the released sourcing setup.
The same sourcing design works for another material family in the same purchasing organization. The sourcing lead wants the issue corrected before the old tracker is retired. Buyers must not override the supplier manually, and the correction must remain standard and transportable because the same sourcing model will be reused in another unit next quarter.
What should the consultant check first?
A regional janitorial-supplies distributor is replacing a branch-level spreadsheet reorder list with standard replenishment planning in SAP S/4HANA Cloud Private Edition. For most consumables, the nightly planning run creates proposals correctly and buyers can continue with downstream procurement tests. However, for one family of low-value disposable items in a newly onboarded branch, the planning log shows the materials as “excluded from net requirements calculation” even though stock is below the expected replenishment threshold and recent withdrawals exist. The same item family produces proposals in an already stabilized branch, and items created directly in the new planning model behave normally.
The program manager wants the branch spreadsheet retired on schedule. Branch planners must not continue parallel manual replenishment beyond the current transition phase, and the correction must remain standard because other branches will adopt the same model next quarter.
What is the most appropriate first action?
<strong>CHALLENGE 2 — Approval Path Stability for Grounded-Aircraft Procurement</strong> During urgent procurement testing, one location can progress grounded-aircraft replacement-part orders fast enough only after local staff alter the intended approval path. The central procurement center wants early live operations to remain manageable through one common release model. What should the validation team do next?