Your customer has created networks with internal activities and generated capacity requirements. Now,
they want to analyze the capacity requirements of their project. Which report do you recommend?
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity.
What controls whether the delivery date is defined by the earliest or latest scheduled dates?
Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers to this question.
What functions are available for period end closing in SAP Project System? Note: There are 3 correct answers to this question
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20.
The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day.
What do you recommend to set up the requirement date for the component ?