問題 1

Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity?
Please choose the correct answer.
Response:
Capacity planning board

問題 2

Assume you have created a sales order for a material to which a strategy group for assembly processing has been assigned and the system automatically created a so-called assembly order in the background and started assembly processing.
In this case, the assembly processing omits which stage and generates an operative order directly from the sales order?
Please choose the correct answer.
Response:

問題 3

In addition to manual planning in the WBS, you sometimes assign different types of orders (internal orders or maintenance orders, for example) to the WBS element that are flagged as account assignment elements. What is the use of this assignment?
There are 3 correct answers to this question.
Response:

問題 4

In which of the following levels can you execute BOM transfer in the order browser?
There are 3 correct answers to this question.
Response:

問題 5

Which indicator automates the grouping of project stock assigned to individual WBS elements to the top WBS element?
Please choose the correct answer.
Response: