Which times elements does MRP consider in backward scheduling to determine he order dates for components from dependent requirements?
Your company produces a finished good based on a forecast and expects it to being stock when customers order it. If customers order more than the forecasted quantity, the production quantity should be increased to try to meet the extra demand. Which planning strategy do you use?
If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?