Which TWO are objectives of the 'closing a project' process?
1. To confirm to the project board that each stage's products are approved
2. To review whether the project was delivered within time and cost tolerances
3. To confirm whether operational staff are happy to take ownership of the products
4. To confirm that there is authority to close the project
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?