問題 1

After a project was delivered, the business analyst learns of a project objective with no associated requirement. What would have helped determine this issue before delivery?

問題 2

A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline.
The business analyst has identified and invited key stakeholders to a requirements workshop. However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end, the business analyst could not elicit and define the requirements and therefore adjourned the meeting.
Which tool or technique could have been used by business analyst to avoid this situation?

問題 3

A business analyst is attempting to elicit requirements on a current project. The business subject matter experts (SMEs) from various departments in the company question how the solution will work with their various systems. Which modeling technique should the business analyst use to depict how the solution will work with all of the company's systems?

問題 4

What should a business analyst do after discovering that two solution requirements conflict?

問題 5

Company A has been awarded a contract to finalize the development of a product that Company B was not able to finish. The business analyst is given a copy of the documentation left by Company B.
To which of the following documents should the business analyst pay the most attention to ensure the project succeeds this time?