問題 1

An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.
Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).

問題 2

In a scrum team, who should be responsible for the budget and release plans?

問題 3

An organization wants to increase value delivery in its agile projects. What should the agile teams do?

問題 4

A company is planning to launch a new service to improve the customer checkout experience. What should the project manager do to meet the objective of reducing time to market to gain a competitive advantage in the industry?

問題 5

A new product owner shares the product vision during the team launch event. The team asks for clarification on the product roadmap and its high-level features.
What should the product owner do?