Project-Management 試験問題を無料オンラインアクセス

試験コード:Project-Management
試験名称:ARE 5.0 Project Management (PjM) Exam
認定資格:NCARB
無料問題数:78
更新日:2026-06-13
評価
100%

問題 1

A construction project is one week away from the date of substantial completion as defined by an AIA A201 agreement. The owner comes forward with a major change to the work. The contractor and owner disagree on how much to extend the contract time. The project needs to proceed without delay while the contractor and owner work out the difference.
Which one of the following steps should the architect take?

問題 2

The architect is on site to evaluate the completed work by the contractor. During the evaluation, the architect notices a structural connection that deviates from the contract documents.
According to AIA B101, to which party should the architect report this observed deviation?

問題 3

Which four factors will most affect the choice of project delivery method? Check the four that apply.

問題 4


Refer to the exhibit.
The following changes occur during the project:
* The owner delayed the project kickoff until September Year 1 due to delays in finalizing the Owner- Architect Agreement.
* The architect did not have enough staff available to start the project on time, so the firm hired temporary staff for 2 months.
* The owner made a design change in January Year 2 that added 2 weeks to the schedule.
* Not enough bids were received, and the project was bid a second time with additional advertising.
* The owner made design changes in May and July of Year 2 that each added 3 weeks to the schedule.
When were the construction documents completed based on the project changes?

問題 5

Preparation of space standards, furniture assessment, and documentation of equipment requirements are most effectively done during which of the following project phases?