74-344 試験問題を無料オンラインアクセス
| 試験コード: | 74-344 |
| 試験名称: | Managing Programs and Projects with Project Server 2013 |
| 認定資格: | Microsoft |
| 無料問題数: | 97 |
| 更新日: | 2026-10-14 |
You are a project manager for an organization that uses Project Server 2013.
Only administrators have Project Professional 2013. You use Project Web App (PWA) for schedule management.
You modify your schedule after some changes are approved through your organization's Project Scope Change process.
You need to set a baseline for the project.
What should you do?
You are a project manager in an organization that uses Project Server 2013. Single-entry mode is disabled. The Only allow task updates via Tasks and Timesheets option is enabled.
Project team members submit updates to tasks through Project Web App (PWA).
A team member submits a status update to you for approval. The team member later
informs you that they made a typing mistake in the status update.
You need to correct the status update.
What should you do?
You are a project manager for an organization that uses Project Server 2013.
As part of a regular project review, you notice that several tasks of one of your projects that should be finished are outdated.
You need to update those tasks with the exact percent complete as of today.
Which three steps should you perform? (Each correct answer presents part of the solution. Choose three.)
Your organization uses Project Online for project portfolio selection. The business drivers and priorities are set, as are the main constraints to identify the efficient frontier.
The company has been collecting business cases for new proposals in which many projects may solve the same business need. For example, the selection for a Customer Relationship Management system has six different proposals, whereas only one is necessary to fulfill the business need.
You need to guarantee that the analysis will produce the most viable proposal in terms of cost and resources and that no repetitive efforts exist in the portfolio selection.
What should you do?
You are a project manager for an organization that uses Project Server 2013. One enterprise project has grown in complexity and size; the project manager creates sub-sites to organize the work by team.
All the teams are comfortable working with a familiar tool, such as the Microsoft SharePoint site. However, management cannot view all of the work being performed in the portfolio, and they need to permanently make decisions about the best use of the resources.
You need to bring all of this work into visibility in the least amount of time and without affecting current resource processes. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)