74-344 試験問題を無料オンラインアクセス

試験コード:74-344
試験名称:Managing Programs and Projects with Project Server 2013
認定資格:Microsoft
無料問題数:97
更新日:2025-08-23
評価
100%

問題 1

You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013.
You review your organization's issue management process.
You need to implement a new issue management process that meets the following requirements:
--
All issues for future projects need to be associated with a source. Source values are either Internal or External.
What should you do?

問題 2

You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. The Project Site Provisioning Mode for your organization allows users to choose when to provision project sites.
You use Project Web App (PWA) to create a new enterprise project named Sub1 that will be inserted as a subproject in your existing master project named Master.
You need to create a new project site for Sub1 as a subsite of the existing Master Project Site.
What should you do?

問題 3

You are a project manager for a company that uses Project Server 2013 in Project Server Permission Mode.
You have been managing a project for several months. You go on vacation, and you delegate your project management responsibility to one of your coworkers.
Your coworker accepts multiple status updates on the project. When you return, you notice that no project updates are visible in Project Web App (PWA), and there are no status updates awaiting approval.
You need to ensure that the previously accepted status updates are visible in PWA.
What should you do?

問題 4

Your organization is in the process of deploying Project Server 2013.
Your business unit manages projects with different tools, such as Microsoft Excel and different versions of Project Professional and Standard. Your business unit needs to upload and manage the projects in the new platform.
You need to guarantee that the projects are uploaded in an efficient way while maintaining data integrity. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

問題 5

You are a program manager for a company that uses Project Server 2013 and Project Professional 2013. You manage the implementation of a data warehouse.
You have set up your program master project with subprojects for each implementation area.
You need to make edits to the dependencies between projects.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)