You are a project manager who uses Project Professional 2013.
Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week.
You need to set up their calendars to reflect the job-sharing arrangement.
What should you do?
Your organization uses Project Professional 2013.
A senior stakeholder informs you that your project start date is delayed and gives you a new start date.
You need to change the project start date without adding constraints.
What are three possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose three.)
You recently updated a schedule by using Microsoft Project.
The vice president of engineering has asked you to show progress only on project milestones and identify milestones falling behind.
You need to find a way to show milestone progress.
Which solution would you meet this objective?
You are a project manager who uses Project Professional 2013.
You are planning an office move, which will occur over a weekend. You use Auto Scheduled tasks and create a weekend working calendar.
You need to assign the weekend working calendar to the task.
What should you do?
You are a project manager who uses Project Standard 2013.
You manage a large project and are capturing actual work for the tasks as they are being worked.
You do not need to enter the time on the actual day worked; however, you need to capture the total amount of time spent on the task.
The fixed work task has a baseline of 20 hours, and the developer's timecard displays the following hours:
* Monday = 2 hours
* Tuesday = 8 hours
* Wednesday = 4 hours
* Thursday = 2 hours
* Friday = 2 hours
The developer informs you that the task is now complete.
You need to update the actual work and mark the task complete.
What should you do?