DRAG DROP
You are a project manager who uses Microsoft Project 2013.
A resource manager notifies you that your assigned resource is now only available 50% to work on the communication plan task. The estimated amount of work for the task remains the same at 16 hours. The task must also be completed within the original two-day commitment even though the resource is only available 50% of the time.
You need to bring on another resource to assist with the remaining 50% of the work while ensuring that the same amount of work gets done in the two days that were originally committed.
Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)
You are a project manager for an organization that uses Project Standard 2013.
You add shortcuts on the Quick Access Toolbar to your most frequently used commands.
Your manager is impressed with the ease of use this customization provides and would like other project managers in the group to use it.
You need to deploy the customization to these project managers.
What should you do?
DRAG DROP
You are a project manager who uses Project Standard 2013.
Your project is approved, and you identify named resources to replace the generic resources for your project tasks.
You need to update the project schedule to assign the named resources to their appropriate tasks.
Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)
You are a project manager who uses Project Professional 2013.
You are creating a project with several phases. Your customer requires the delivery phase of the project to start on July 1 and to finish within four weeks. The delivery phase includes a summary task, which consists of five separate sub tasks.
You need to monitor this phase closely to ensure that it does not overrun.
What should you do?
You are a project manager who uses Microsoft project.
Your manager wants you to plan an office move. You have a project schedule from a prior office move named OfficeMove.mpp.
You need to create a new project schedule based on the old project schedule by performing the fewest steps possible.
What should you do?