問題 1

You need to view only the task name, start and finish dates, percentage of work completed, and a Gantt chart. What should you do?

問題 2

Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?

問題 3

You manage several projects saved on a shared drive. You want to create a critical path relationship between several schedules managed by other project managers. You need to link the project schedules at the task level. You also need to ensure that each project manager can continue to manage their own project. What should you do?

問題 4

You have a Project 2010 schedule that contains the following tasks: Inactive tasks Manually scheduled tasks Manually scheduled summary tasks Tasks that contain strikethrough font You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are created. What should you do?

問題 5

The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?