You are in the Project Management Office (PMO) for a company that uses Project Online to select portfolios for each business unit.
The parameters used as cost constraints vary from department to department, including Cost, CapEx, and Estimated Hours. You are responsible for providing the infrastructure to support the various constraints.
You need to select a feasible method for employing cost constraints.
Which two fields should you use? (Each correct answer presents part of the solution. Choose two.)
Your organization is in the process of deploying Project Server 2013.
Your business unit manages projects with different tools, such as Microsoft Excel and different versions of Project Professional and Standard. Your business unit needs to upload and manage the projects in the new platform.
You need to guarantee that the projects are uploaded in an efficient way while maintaining data integrity. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A company deploys Project Server 2013 to perform a Portfolio Analysis, which they will use to select the projects they will execute in the next fiscal period.
The company establishes the criteria to evaluate the portfolio components, and all business cases must be evaluated under these parameters. When configuring Project Server 2013, the Project Management Office (PMO) finds that the established criteria contain both qualitative and quantitative elements, such as corporate reputation and internal rate of return (IRR).
You need to provide a system calculated approach to rank your strategic initiatives against each other. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
You are a program manager for an organization that uses Project Server 2013.
You work in a master project, which contains ten sub-projects. One of your project managers makes changes to a sub-project and publishes it.
You open the master project and realize that these changes are not reflected in the master project schedule.
You need to ensure these changes are reflected in the master project.
What should you do?
DRAG DROP
You are a project manager for an organization that uses Project Server 2013.
You check out a project for editing in Project Professional 2013 and discover that one resource is overallocated across three projects.
You need to determine the cause of the overallocation by using the Team Planner view to resolve the issue.
Which four actions should you perform in sequence? (To answer, move the appropriate four actions from the list of actions to the answer area and arrange them in the correct order.)