074-343 試験問題を無料オンラインアクセス

試験コード:074-343
試験名称:Managing Projects with Microsoft Project 2013
認定資格:Microsoft
無料問題数:110
更新日:2026-07-30
評価
100%

問題 1

You are a resource manager who uses Project Standard 2013.
You manage all of your resources in a single plan, which acts as a Shared Resource Pool for other projects in your organization. Each resource needs to pass an annual exam in order to work on construction sites.
You need to set up a method that allows you to pick the renewal month for each resource.
What should you do?

問題 2

You are a project manager who uses Microsoft Excel 2013.
Your company decides to migrate all of the current projects in Microsoft Excel 2013 to Project Professional 2013. They allow all employees to spend 8 hours migrating each project plan. Your current and unique project plan has 462 tasks with duration in days, and resources have been assigned and named. You have a status meeting in two days.
You need to provide your project's information by using Project Professional 2013.
What should you do?

問題 3

You are a project manager who uses Project Standard 2013.
You regularly customize the Bar Styles for a project prior to printing the project schedule.
You need to add the Bar Styles button to the Quick Access Toolbar as quickly as possible.
What are two ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)

問題 4

You are using Project Standard 2013.
You want the ability to see only tasks that have finish dates past their deadline date You need to achieve this goal using a custom field.
What should you do?

問題 5

You are a project manager, and your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks.
You create two manually scheduled tasks and link them in a Finish to Start relationship.
The project team member asks you to increase the duration of the predecessor task.
You notice that the successor task start date is now before the finish date of the predecessor task.
You want the successor task to start after the predecessor finishes.
What should you do?

コメントを追加

あなたのメールアドレスが公開されることはありません。個人情報に関する内容は隠されます *

insert code
画面にある文字を入力してください。