A company is expanding its production capability. A project manager is assigned to bring a team of stakeholders together to conduct an analysis of the situation and develop a plan. During the analysis, the project manager gains an understanding of what resources stakeholders are willing to commit, the stakeholders' expectations, and what the stakeholders have to gain from the project. This analysis is MOST likely to identify which of the following?
A supply manager is reviewing safety stock for a particular unit. The unit is small, Inexpensive, non-perishable, and easily stored, but is critical to the firm's manufacturing process. The following information is known about this unit:
Maximum lead time = 8 Days
Average lead time = 3 Days
Maximum daily usage = 6,000 Units
Average daily usage = 4,000 Units
What is the maximum safety stock that should be maintained for this unit?
A scientific equipment company wants to encourage its key suppliers to participate in the firm's quality certification program. The process is detailed and time-consuming. Which of the following is likely to be the GREATEST benefit to the buying organization?