問題 1

The widget production project is well underway. The requirements are clear that each widget must weigh between 0.320 and 0.325 ounces. The first day of test production resulted in 1247 widgets. Of the widgets inspected, 47 percent fell within the acceptable weight range. This is an example of:

問題 2

Which process occurs within the Monitoring and Controlling Process Group?

問題 3

What is the tool and technique used to request seller responses?

問題 4

What is the schedule performance index (SPI) using the following data?
BAC = $100,000
PV = $50,000
AC = $80,000
EV = $40,000

問題 5

The project charter is developed by: