Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.
Why may this be the case?
All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads "Project cannot be marked Complete if there are open issues and tasks that are not complete." How can the Project Owner determine which tasks are incomplete?
What occurs when an individual enters a new commit date that is after the original planned date of a task?
A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.
What action should the task owner take?