問題 1

Which of the following are not typical responses to risks?
* Complete root cause analysis to understand why the situation has occurred.
* Reduce the probability of the threat occurring or the impact on the project.
* Change objectives or practices to change the cause of the threat so it can no longer occur.
* There are no acceptable or viable approaches to take to avoid or reduce, so the threat and any residual risk must be managed.
* Prepare a risk management plan to document the risk and give it to your sponsor.
* Pass the responsibility for bearing the impact of the threat from one party to another.

問題 2

Quality control activities help to prevent problems being passed on to customers. State two quality control checks that may be carried out during a project:

問題 3

Explain how business-as-usual activities can impact the project schedule, considering each of the following elements:

問題 4

Which of the below would not usually be recorded within a change request?

問題 5

Which of the activities below would provide final assurance of a project?