A company uses Dynamics 365 Supply Chain Management for Process manufacturing.
You are reviewing the planned production orders for the next two weeks. There are several production orders for the same product. One order is scheduled to run the week after another order.
You need to optimize the planned production orders.
What should you do?
A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.
The production planner increases the lead time of an item. On the next master planning output the planner receives a cancel action message on existing purchase orders. The message includes a suggested earlier date for the planned purchase orders.
The demand for the item has not changed since the original purchase order was placed. Dynamic negative days is not used.
You need to resolve the issue.
What should you do?
You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.
A machine in the facility is defective and must be closed for repairs for the next two days.
You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?
A manufacturing company is implementing production in Dynamics 365 Supply Chain Management.
The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling in a graphical view.
You need to configure the system to meet the requirements.
Which three options should you configure? Each answer presents a partial solution.
NOTE: Each correct selection is worth one point.
An electronics manufacturing company is transitioning from infinite capacity planning to finite capacity planning to improve scheduling efficiency and manage resource constraints effectively.
The company observes that its manufacturing process typically requires a minimum lead time of five days.
The company requires finite capacity scheduling to create realistic production schedules that account for resource limitations over a defined minimum lead time of five days.
You need to implement finite capacity planning with a time fence that aligns with the five-day manufacturing lead time.
Solution: Set a finite capacity time fence for one day of manufacturing.
Does the solution meet the goal?